Improvements to Electricity Supply in Huyton

Published on: Friday, 20-June-2014

SP Energy Networks are installing a new 33,000 Volt cable through Huyton to improve service to the area and reduce the number of power interruptions that occur.

The new cable will be laid along Liverpool Road, South Alt Gateway Park, Cassino Road, Stanley Road, Rupert Road, Archway Road, Poplar Bank, Derby Road, Huyton Hey Road and Wilson Road. There will be NO planned interruption to power supply during these works.

The work will be completed in 5 stages and during each stage only a small length of excavation will occur to minimise disruption. Work started on Wilson Road on 2 June and is due to be completed in the last few months of this year.

To discuss the work, you can call SP Energy Networks on 0845 273 4444

Or visit www.spenergynetworks.com/pages/general_enquiry_form.asp